Mathematical approach for better mine waste rock dumping management
Access Status
Authors
Date
2012Type
Metadata
Show full item recordCitation
Source Title
Source Conference
ISBN
Collection
Abstract
A mine waste rock dump does not have any intrinsic value, yet is an inevitable structure in surface mining operations. Since the purpose of mining is to maximise profit, possible expenditure reduction in hauling waste rock to the dump, which can represent up to 50% of the total operating cost, is highly desirable. Apart from cost, potential acid mine drainage (AMD), due to seepage from surface waste rock dumps containing reactive waste rock, could threaten the ecological balance, drinking water supplies and irrigation systems downstream from a mine site. In order to minimise these potential risks, selective placement of benign and reactive waste rock, and the encapsulation of reactive waste rock by benign rock, need to be carried out during the construction of the dump. In this paper, a new methodology, based on mixed integer programming (MIP) is developed to manage waste rock dumping. The model aims to minimise waste rock haulage costs by locating the optimum destination(s) for each waste block, while at the same time controlling the placement of reactive waste rock to minimise the potential for AMD. Tests on small-scale virtual data demonstrated that the model is capable of dealing with selective placement of different waste rock types, encapsulating reactive, potentially acid forming (PAF) waste rock, and stockpiling benign waste rock for encapsulation and rehabilitation purposes. The solution time for the MIP model is far less than the traditional manual approach, and the resulting schedule is up to 30% more cost-effective.
Related items
Showing items related by title, author, creator and subject.
-
Li, Yu; Topal, Erkan; Williams, David (2013)Despite the fact that waste rock hauling and dumping comprises a large proportion of the cost of materials handling in an open pit mine, little detailed planning is devoted to optimising waste rock dumping. The lack of ...
-
Li, Y.; Topal, Erkan; Williams, D. (2014)Cost reduction via optimising the scheduling of waste rock placement has a very high potential of success, as large volumes of waste rock are involved in operating an open pit mine, along with high rehabilitation costs. ...
-
Fu, Z.; Asad, Mohammad Waqar; Topal, Erkan (2019)An open-pit mine schedule defines the optimal sequence of mining valuable (ore) and waste material with the objective of maximizing the value of the project. Given this production schedule, a waste-dump schedule is then ...