Factors Influencing Delay in Construction/Civil Engineering Projects in the Persian Gulf Countries
Access Status
Authors
Date
2012Type
Metadata
Show full item recordCitation
Source Title
Source Conference
ISBN
Collection
Abstract
A large number of projects around the world experience extensive delays; that is to say they go beyond initial time and cost estimates. There are various causes of delay in different countries including social, economical, political, environmental and religious issues. Severe weather conditions, heavy rains and floods are the most important causes of delay in road construction projects in Central Africa; on the other hand, in the Middle East, many delays are due to ineffective planning, shortage of labour and workmanship, whilst in West Central Asia many constructional delays are caused by changing orders and owners financial constraints. The work presented here discusses the extent to which geographical location and socio-economic variables affect construction delay generally, and examines in particular the main reasons of delay (and a means to address and mitigate such delay) in construction projects in the Persian Gulf. The work explores key factors of delay related to reliance of construction budget(s) upon oil price in locations where 85% of the national construction and infrastructure budget is derived from the oil income, and where fluctuations in dollar-per-barrel costs have a knock-on effect for construction project interim payments and final accounting to allow practical completion; discussion is made (in this early-stage research-project discussion paper) of an accurate means to predict and then allocate risk and fluctuation allowances into both the pre-contract feasibility stage as well as on-site activities directed and controlled by contractual arrangement.
Related items
Showing items related by title, author, creator and subject.
-
Alotaibi, Nasser Obaid; Sutrisna, Monty; Chong, Heap Yih (2016)Delays can be considered a common problem within public and private construction projects around the world but the problem is endemic in Kingdom of Saudi Arabia (KSA) where massive public funds are lost every year as a ...
-
Wang, T.; Ford, D.; Chong, Heap Yih; Zhang, W. (2018)Purpose: Delays during construction are one of the common scenarios in the construction industry. The purpose of this paper is to identify the primary causes of delays in the construction phase of building construction ...
-
Han, Sangwon; Love, Peter; Peña-Mora, Feniosky (2013)Design errors leading to rework and/or design changes are considered to be the primary contributor to schedule delays and cost overruns in design and construction projects. While design errors are deemed prevalent, most ...