Probability distribution fitting of schedule overruns in construction projects
Access Status
Authors
Date
2013Type
Metadata
Show full item recordCitation
Source Title
ISSN
Collection
Abstract
The probability of schedule overruns for construction and engineering projects can be ascertained using a ‘best fit’ probability distribution from an empirical distribution. The statistical characteristics of schedule overruns occurring in 276 Australian construction and engineering projects were analysed. Skewness and kurtosis values revealed that schedule overruns are non-Gaussian. Theoretical probability distributions were then fitted to the schedule overrun data; including the Kolmogorov–Smirnov, Anderson–Darling and Chi-Squared non-parametric tests to determine the ‘Goodness of Fit’. A Four Parameter Burr probability function best described the behaviour of schedule overruns, provided the best overall distribution fit and was used to calculate the probability of a schedule overrun being experienced. The statistical characteristics of contract size and schedule overruns were also analysed, and the Wakeby (<AU$1 m and AU$11–50 m), Three Parameter Log-logistic (AU$1–A$10 m) and Beta (AU$51–A$100 m and >AU$101 m) models provided the best distribution fits and were used to calculate schedule overrun probabilities by contract size.
Related items
Showing items related by title, author, creator and subject.
-
Love, Peter; Sing, Michael; Wang, Xiangyu; Irani, Z.; Thwala, D. (2014)Transportation infrastructure projects are prone to cost and schedule overruns. At the time of contract award, a construction contingency budget is often used to accommodate for unplanned events such as scope changes. ...
-
Love, Peter; Sing, Michael; Wang, Xiangyu; Yung, Ping; Odeyinka, H. (2012)The probability of schedule overruns on construction projects can be ascertained using a 'best fit' probability distribution from an empirical distribution. The statistical characteristics of schedule overruns occurring ...
-
Love, Peter; Wang, Xiangyu; Sing, Michael; Tiong, Robert (2013)The statistical characteristics of cost overruns experienced from contract award in 276 Australian construction and engineering projects were analyzed. The skewness and kurtosis values of the cost overruns are computed ...