A Conceptual Framework of Quality-Assured Fabrication, Delivery and Installation Processes for Liquefied Natural Gas (LNG) Plant Construction
Access Status
Authors
Date
2015Type
Metadata
Show full item recordCitation
Source Title
ISSN
School
Collection
Abstract
© 2014, Springer Science+Business Media Dordrecht. Construction productivity issues in the Liquefied Natural Gas (LNG) construction industry can lead to project cost blowouts. Time wasted by construction personnel getting the right information on megaprojects can be a substantial contributing factor. It appears that the communication on site is not cost effective, judging by the number of large project that have experienced budget overruns in the past. More importantly, as-built design documentation often fails the quality test, resulting in operational inefficiencies once the plant has been handed over from Construction to Operation Phase. Common errors during the static prefabrication, dispatch and installation processes can result in serious rework as a significant amount of construction time and budget is wasted. To minimise these problems, this paper recommends to better control the dynamic natures of construction. This study propagates a conceptual framework for assuring quality of modular construction in LNG plants by introducing a Situation Awareness construction environment with well-defined sensing and tracking technologies. While encountering situations inconsistent with plans during construction, such as time delay, fabrication errors, conflicts in terms of accessibility and constructability issues and so forth, sensors mounted in situ can discover such situations and recursively fed back to field personnel. Automation and robotics technologies, such as real-time path planning, collision detection and deviation examination utilizing as-planned building information model, can assist engineers to rapidly react with inconsistent situations and make acceptable decisions instead of partially or entirely suspending the workforce through massive reworks. In this study, we conduct a preliminary study in demonstrating the feasibility of utilizing sensory devices and automatic planning technologies. The expected results of adopting the framework are the quality-assured modular construction and execution plans during construction stages to save rework construction time and budget.
Related items
Showing items related by title, author, creator and subject.
-
Earnest, James (2011)Rehabilitation and reconstruction of social and economic infrastructure in a post-conflict environment are complex and long-debated issues in development cooperation. Both in pre-conflict and post-conflict situations, ...
-
Sluter, C.; Brandalize, M.; Ivanova, Ivana; van Elzakker, C. (2013)This paper describes the first step of a research project that aims to establish a standard set of symbols for the cartographic representation of urban regions. This first step is a case study that focuses on street network ...
-
Jaggar, D.; Love, Peter; Smith, J.; Olatunji, O. (2016)Cost management of all building projects has become increasingly important as clients in the public and private sector demand the highest quality cost planning services with accurate budgeting and cost control. All members ...