    A study of the factors affecting construction time in Western Australia

    Access Status
    Fulltext not available
    Authors
    Wong, K.
    Vimonsatit, Vanissorn
    Date
    2012
    Type
    Journal Article
    
    Metadata
    Show full item record
    Citation
    Wong, Kenny and Vimonsatit, Vanissorn. 2012. A study of the factors affecting construction time in Western Australia. Scientific Research and Essays. 7 (40): pp. 3390-3398.
    Source Title
    Scientific Research and Essays
    Additional URLs
    http://academicjournals.org/article/article1380791729_Wong%20and%20Vimonsatit.pdf
    ISSN
    1992-2248
    URI
    http://hdl.handle.net/20.500.11937/5374
    Collection
    • Curtin Research Publications
    Abstract

    Delays are major problems that face the Western Australia’s construction industry. Delays can lead to many negative effects such as cost overruns, and is of high concern to those who are involved in the construction industry. This study was set to identify the major causes of delays in the Western Australian construction industry, by means of a literature review and a questionnaire survey. A total of 48 delay factors were obtained from literature review and were further categorised into eight major groups that contributed to the causes of delay. The questionnaire survey was distributed to the targeted respondents from a combination of clients, contractors, and consultants in Perth, Western Australia. About 32 respondents participated in the survey. Based on the data received, albeit limited, the top ten most important causes identified were: (1) Shortage of skills; (2) Financial difficulties; (3) Shortage of labour; (4) Unrealistic deadlines for project completion; (5) Unforeseen ground conditions; (6) Poor organization of the contractor or consultant; (7) Poor communication; (8) Underestimation of time of completion; (9) low speed of decision; and (10) Design errors made by designers.

    Related items

    Showing items related by title, author, creator and subject.

    • An investigation of the physiological and biochemical responses elicited by Panulirus cygnus to harvesting, holding and live transport.
      Spanoghe, Patrick T. (1996)
      The western rock lobster (WRL), Panulirus cygnus is a decapod crustacean which is found in abundance in the coastal waters of Western Australia and which supports a major fishery of economic importance for the State, with ...
    • Computational methods for solving optimal industrial process control problems
      Chai, Qinqin (2013)
      In this thesis, we develop new computational methods for three classes of dynamic optimization problems: (i) A parameter identification problem for a general nonlinear time-delay system; (ii) an optimal control problem ...
    • Enabling an effective knowledge and information flow between the phases of building construction and facilities management
      Tan, A.; Zaman, Atiq; Sutrisna, Monty (2018)
      Purpose The purpose of this study is to investigate ways of transferring knowledge and information during the life-cycle phases of construction projects, particularly between the construction and occupancy phases, and to ...
    Advanced search

    Browse

    Communities & CollectionsIssue DateAuthorTitleSubjectDocument TypeThis CollectionIssue DateAuthorTitleSubjectDocument Type

    My Account

    Admin

    Statistics

    Most Popular ItemsStatistics by CountryMost Popular Authors

    Follow Curtin

    • 
    • 
    • 
    • 
    • 

    CRICOS Provider Code: 00301JABN: 99 143 842 569TEQSA: PRV12158

    Copyright | Disclaimer | Privacy statement | Accessibility

    Curtin would like to pay respect to the Aboriginal and Torres Strait Islander members of our community by acknowledging the traditional owners of the land on which the Perth campus is located, the Whadjuk people of the Nyungar Nation; and on our Kalgoorlie campus, the Wongutha people of the North-Eastern Goldfields.