    System information modelling in practice: Analysis of tender documentation quality in a mining mega-project

    Access Status
    Fulltext not available
    Authors
    Love, Peter
    Zhou, Jingyang
    Matthews, Jane
    Sing, M.
    Edwards, D.
    Date
    2017
    Type
    Journal Article
    
    Metadata
    Show full item record
    Citation
    Love, P. and Zhou, J. and Matthews, J. and Sing, M. and Edwards, D. 2017. System information modelling in practice: Analysis of tender documentation quality in a mining mega-project. Automation in Construction. 84: pp. 176-183.
    Source Title
    Automation in Construction
    DOI
    10.1016/j.autcon.2017.08.034
    ISSN
    0926-5805
    School
    Department of Civil Engineering
    URI
    http://hdl.handle.net/20.500.11937/58939
    Collection
    • Curtin Research Publications
    Abstract

    © 2017 Elsevier B.V. The quality of information contained in tender documentation produced using Computer-Aided-Design (CAD) and provided in a hard-copy format to an electrical engineering contractor for a port expansion facility, which formed an integral part of an Iron Ore mega-project is analyzed. A System Information Model (SIM), which is an object oriented approach, was retrospectively constructed from the documentation provided to assist the contractor with their tender bid preparation. During the creation of the SIM, a total of 426 errors and omissions were found to be contained within the 77 tender ‘drawing’ documents supplied to the contractor by an Engineering, Construction, Procurement and Management (EPCM). Surprisingly, 70 drawings referenced in the tender documentation, and the Input/Output lists and Cause/Effect drawings were not provided. Yet, the electrical contractor was required by the EPCM organization to provide a lump sum bid and also guarantee the proposed schedule would be met; the financial risks were too high and as a result the contractor decided not to submit a bid. It is suggested that if the original tender documentation had been prepared using a SIM rather than CAD, the quality of information presented to the contractor would have enabled them to submit a competitive bid for the works. The research concludes that the economic performance and productivity of mining projects can be significantly improved by using a SIM to engineer and document electrical instrumentation and control (EIC) systems.

    Related items

    Showing items related by title, author, creator and subject.

    • Impact of contractor internal tendering procedure governance on tender win-rates: How procedures can be improved
      Urquhart, Stephen ; Whyte, Andrew (2018)
      Construction contractors normally, though not always, pursue tenders with the expectation of winning and subsequently making a project profit. Corporate governance (CG) constraints, risk appetite, and selected tender ...
    • Implications of governance obligations being embedded within construction contractors’ tendering procedures
      Urquhart, Stephen ; Whyte, Andrew (2020)
      © 2020 Engineers Australia. Construction contractors’ (contractors) internal tendering procedures (ITP) face increasing governance obligations, either through corporate regulations, legislation and/or societal expectations. ...
    • Contractor tendering research: Going beyond bid/no-bid and markup models
      Urquhart, Stephen ; Whyte, Andrew (2018)
      Within a wider research programme into the effectiveness and efficiency of the tendering procedures of construction contractors (CCs), a content analysis of tender research published in 27 journals between 2010 and 2016 ...
    Advanced search

    Browse

    Communities & CollectionsIssue DateAuthorTitleSubjectDocument TypeThis CollectionIssue DateAuthorTitleSubjectDocument Type

    My Account

    Admin

    Statistics

    Most Popular ItemsStatistics by CountryMost Popular Authors

    Follow Curtin

    • 
    • 
    • 
    • 
    • 

    CRICOS Provider Code: 00301JABN: 99 143 842 569TEQSA: PRV12158

    Copyright | Disclaimer | Privacy statement | Accessibility

    Curtin would like to pay respect to the Aboriginal and Torres Strait Islander members of our community by acknowledging the traditional owners of the land on which the Perth campus is located, the Whadjuk people of the Nyungar Nation; and on our Kalgoorlie campus, the Wongutha people of the North-Eastern Goldfields.