    Managing Critical Factors Causing Delays in Public Construction Projects in the Kingdom of Saudi Arabia

    Alotaibi N 2018.pdf (3.743Mb)
    Access Status
    Open access
    Authors
    Alotaibi, Nasser Obaid M
    Date
    2018
    Supervisor
    Monty Sutrisna
    Type
    Thesis
    Award
    PhD
    
    Metadata
    Show full item record
    Faculty
    Humanities
    School
    School of Design and the Built Environment
    URI
    http://hdl.handle.net/20.500.11937/70732
    Collection
    • Curtin Theses
    Abstract

    This thesis examines factors contributing to delays in public construction projects in Kingdom of Saudi Arabia (KSA) and the implications of applying project management knowledge, tools, and techniques in addressing the problem. Using a triangulation research approach, this study identifies factors influencing public construction delays in KSA and current knowledge of PM concepts for minimising construction delays. Based on the results from qualitative and quantitative studies undertaken, a framework for minimising delays was developed.

    Related items

    Showing items related by title, author, creator and subject.

    • Computational methods for solving optimal industrial process control problems
      Chai, Qinqin (2013)
      In this thesis, we develop new computational methods for three classes of dynamic optimization problems: (i) A parameter identification problem for a general nonlinear time-delay system; (ii) an optimal control problem ...
    • Guidelines of Using Project Management Tools and Techniques to Mitigate Factors Causing Delays in Public Construction Projects in Kingdom of Saudi Arabia
      Alotaibi, Nasser Obaid; Sutrisna, Monty; Chong, Heap Yih (2016)
      Delays can be considered a common problem within public and private construction projects around the world but the problem is endemic in Kingdom of Saudi Arabia (KSA) where massive public funds are lost every year as a ...
    • Stability and control of switched systems with impulsive effects
      Xu, Honglei (2009)
      Switched systems belong to a special class of hybrid systems, which consist of a collection of subsystems described by continuous dynamics together with a switching rule that specifies the switching between the subsystems. ...
    Advanced search

    Browse

    Communities & CollectionsIssue DateAuthorTitleSubjectDocument TypeThis CollectionIssue DateAuthorTitleSubjectDocument Type

    My Account

    Admin

    Statistics

    Most Popular ItemsStatistics by CountryMost Popular Authors

    Follow Curtin

    • 
    • 
    • 
    • 
    • 

    CRICOS Provider Code: 00301JABN: 99 143 842 569TEQSA: PRV12158

    Copyright | Disclaimer | Privacy statement | Accessibility

    Curtin would like to pay respect to the Aboriginal and Torres Strait Islander members of our community by acknowledging the traditional owners of the land on which the Perth campus is located, the Whadjuk people of the Nyungar Nation; and on our Kalgoorlie campus, the Wongutha people of the North-Eastern Goldfields.