dc.identifier.citationLove, P.E.D. and Matthews, J. and Ika, L.A. 2023. Fast-and-frugal heuristics: an exploration into building an adaptive toolbox to assess the uncertainty of rework. Production Planning and Control.
dc.identifier.urihttp://hdl.handle.net/20.500.11937/94766
dc.identifier.doi10.1080/09537287.2023.2257178
dc.description.abstract

Performing rework within the production system of construction is the most expensive waste that confronts organisations, with its causation yet to be fully understood in practice. Any effort to assess the risk of rework poses challenges due to limited information about its frequency and causes, rendering the use of statistical models immeasurable. Research has shown that fast-and-frugal heuristics enable epistemic success under conditions of uncertainty and cognitive complexity–they are accurate, fast, and rely on limited information. Thus, this paper proposes the following research question: How can fast-and-frugal heuristics effectively assess the uncertainty of rework in construction? The theoretical framing of ecological rationality provides an environmental structure for bounded rationality to explore this question, enabling a person’s ‘adaptive toolbox’ of fast-and-frugal heuristics tailored for different epistemic and pragmatic decisions to be utilised. Situations during the construction of a transport infrastructure mega-project (>AU$18 billion) where there was profound uncertainty surrounding rework are presented. The heuristics, intuitively drawn from an individual’s adaptive toolbox used to form judgments to assess the uncertainty of rework, are identified. The theoretical and practical implications of the paper are discussed before presenting suggestions for future research to help build a robust adaptive toolbox to be utilised for assessing the uncertainty of rework in construction.

dc.relation.sponsoredbyhttp://purl.org/au-research/grants/arc/DP210101281
dc.rights.urihttp://creativecommons.org/licenses/by-nc-nd/4.0/
dc.titleFast-and-frugal heuristics: an exploration into building an adaptive toolbox to assess the uncertainty of rework
dc.typeJournal Article
dcterms.source.issn0953-7287
dcterms.source.titleProduction Planning and Control
dc.date.updated2024-04-09T06:32:09Z
curtin.departmentSchool of Civil and Mechanical Engineering
curtin.accessStatusOpen access
curtin.facultyFaculty of Science and Engineering
curtin.contributor.orcidLove, Peter [0000-0002-3239-1304]
curtin.contributor.researcheridLove, Peter [D-7418-2017]
dcterms.source.eissn1366-5871
curtin.contributor.scopusauthoridLove, Peter [7101960035]
curtin.repositoryagreementV3


Files in this item

Thumbnail

This item appears in the following Collection(s)

Show simple item record

http://creativecommons.org/licenses/by-nc-nd/4.0/
Except where otherwise noted, this item's license is described as http://creativecommons.org/licenses/by-nc-nd/4.0/