Time-cost relationships in Australian building construction projects
Access Status
Authors
Date
2005Type
Metadata
Show full item recordCitation
Source Title
ISSN
Collection
Abstract
Project time–cost relationships were examined by using project scope factors as predictors for 161 construction projects that were completed in various Australian States using the multiple regression technique of weighted least squares. The analysis was performed between project duration (i.e., time), project type, procurement method, tender type, gross floor area (GFA), and number of stories. An alternative model to that proposed by Bromilow more than three decades ago for forecasting time and cost performance is proposed. It is shown that GFA and the number of stories in a building are key determinants of time performance in projects. Furthermore, the results indicate that cost is a poor predictor of time performance. Limitations and practical implications of the research are also presented.
Related items
Showing items related by title, author, creator and subject.
-
Chen, Q.; Jin, Z.; Xia, B.; Wu, Peng; Skitmore, M. (2016)© 2015 American Society of Civil Engineers. The design-build (DB) delivery method has been widely used in the United States due to its reputed superior cost and time performance. However, rigorous studies have produced ...
-
Odhigu, F.; Yahya, Azhar; Rani, N.; Shaikh, Junaid (2012)This research investigated the impacts of procurement systems on the performance of construction projects in East Malaysia. Construction project outcome is measured in terms of time, cost and quality achieved. Project ...
-
Colegate, Timothy Maarten (2012)The Square Kilometre Array (SKA) radio telescope is being designed as a premier scientific instrument of the 21st century, using novel technologies to maximise its scientific capability. The SKA has an aggressive project ...