Divergence or Congruence? A Path Model or Rework for Building and Civil Engineering Projects
Access Status
Authors
Date
2009Type
Metadata
Show full item recordCitation
Source Title
ISSN
School
Collection
Abstract
Rework has been identified as a major contributor to cost and schedule overrun in construction projects. Previous studies that have examined rework are based on a limited data sets and thus eschew generalizations being made about the key determinants. Using data from 260 completed building (n=147) and civil engineering (n=113) projects, path analysis is used to develop a structural model of the most significant causes of rework. The model revealed that the paths of client-directed changes, site management and subcontractors, and project communication were statistically significant contributors to rework costs. The analysis confirmed that the lack of attention to quality management resulted in higher rework costs being incurred in the projects sampled. The analysis also revealed that there were no significant differences between building and civil engineering projects in terms of the direct and indirect cost of rework experienced, and the effectiveness of the project management practices implemented. Considering the findings, it is suggested that generic strategies for reducing the incidence rework in construction and civil engineering projects can be developed.
Related items
Showing items related by title, author, creator and subject.
-
Ekambaram, P.; Love, Peter; Kumaraswamy, M.; Ng, T. (2014)Purpose – Rework is an endemic problem in construction projects and has been identified as beinga significant factor contributing cost and schedule overruns. Causal ascription is necessary to obtainknowledge about the ...
-
Forcada, N.; Alvarez, A.; Love, Peter; Edwards, D. (2017)© 2016 American Society of Civil Engineers. There is a paucity of systematic knowledge on the dynamics of rework in urban renewal projects even though such projects frequently exceed budget and schedule. The causal factors ...
-
Love, Peter; Sing, Michael (2013)Rework arises due to design errors, changes and omissions during design and has been found to contribute to 52% of a project’s cost overrun. The statistical characteristics of rework costs experienced from contract award ...