    The costs of rework: insights from construction and opportunities for learning

    73141.pdf (953.7Kb)
    Access Status
    Open access
    Authors
    Love, Peter
    Smith, J.
    Ackermann, Fran
    Irani, Z.
    Teo, Pauline
    Date
    2018
    Type
    Journal Article
    
    Metadata
    Show full item record
    Citation
    Love, P. and Smith, J. and Ackermann, F. and Irani, Z. and Teo, P. 2018. The costs of rework: insights from construction and opportunities for learning. Production Planning & Control.
    Source Title
    Production Planning & Control
    DOI
    10.1080/09537287.2018.1513177
    ISSN
    0953-7287
    School
    School of Civil and Mechanical Engineering (CME)
    Funding and Sponsorship
    http://purl.org/au-research/grants/arc/DP130103018
    URI
    http://hdl.handle.net/20.500.11937/72898
    Collection
    • Curtin Research Publications
    Abstract

    © 2018, © 2018 Informa UK Limited, trading as Taylor & Francis Group. During the production of artefacts in construction, there is a likelihood for errors to be committed, which may need to be rectified so that they conform to defined contractual requirements and standards. In doing so, this initiates a process of rework, which is a problem that the industry has incessantly aimed to redress for decades with limited success. Rework is a ‘known-unknown’, but there remains a high degree of uncertainty about its costs. Such uncertainty occurs as there is a proclivity for the costs associated with rework to be largely ignored, concealed or considered to be normal function of operations. This paper presents the results from the first longitudinal and in-depth study of rework costs in construction. Based on a sample of 19,605 rework events derived from 346 construction projects delivered by a contractor between the years 2009 and 2015, it was revealed that their mean yearly profit over the period of analysis was reduced by a staggering 28%. In addition, 88 (0.45%) of the total 19,605 rework events accounted for 34% of the total costs that were incurred. The complete cost data for 98 of the 346 projects was made available, which enabled a mean rework cost of 0.39% of contract value to be determined. The research provides construction organizations with an improved understanding of the nature and likelihood of rework costs enabling them to move from a position of being a ‘known-unknown’ to becoming a ‘known-known’. Being able to ‘anticipate what might go wrong’ and ensure that risk management and controls are put in place throughout the construction process will contribute to their dynamic capability.

    Related items

    Showing items related by title, author, creator and subject.

    • Overruns in Transportation Infrastructure Projects
      Love, Peter; Sing, Michael; Wang, Xiangyu; Irani, Z.; Thwala, D. (2014)
      Transportation infrastructure projects are prone to cost and schedule overruns. At the time of contract award, a construction contingency budget is often used to accommodate for unplanned events such as scope changes. ...
    • Determining the probability distribution of rework costs in construction and engineering projects
      Love, Peter; Sing, Michael (2013)
      Rework arises due to design errors, changes and omissions during design and has been found to contribute to 52% of a project’s cost overrun. The statistical characteristics of rework costs experienced from contract award ...
    • A rework probability model: A quantitative assessment of rework occurrence in construction projects
      Simpeh, E.; Ndihokubwayo, R.; Love, Peter; Thwala, W. (2015)
      © 2015 Taylor & Francis. Statistical methods for eliciting probability distributions were used to analyse the data collected from 78 construction professionals. The empirical distributions for rework costs were found to ...
    Advanced search

    Browse

    Communities & CollectionsIssue DateAuthorTitleSubjectDocument TypeThis CollectionIssue DateAuthorTitleSubjectDocument Type

    My Account

    Admin

    Statistics

    Most Popular ItemsStatistics by CountryMost Popular Authors

    Follow Curtin

    • 
    • 
    • 
    • 
    • 

    CRICOS Provider Code: 00301JABN: 99 143 842 569TEQSA: PRV12158

    Copyright | Disclaimer | Privacy statement | Accessibility

    Curtin would like to pay respect to the Aboriginal and Torres Strait Islander members of our community by acknowledging the traditional owners of the land on which the Perth campus is located, the Whadjuk people of the Nyungar Nation; and on our Kalgoorlie campus, the Wongutha people of the North-Eastern Goldfields.