    The latent causes of rework in floating production storage and offloading projects

    Access Status
    Fulltext not available
    Authors
    Love, Peter
    Edwards, D.
    Irani, Z.
    Forcada, N.
    Date
    2014
    Type
    Journal Article
    
    Metadata
    Show full item record
    Citation
    Love, P. and Edwards, D. and Irani, Z. and Forcada, N. 2014. The latent causes of rework in floating production storage and offloading projects. Journal of Civil Engineering and Management. 20 (3): pp. 315-329.
    Source Title
    Journal of Civil Engineering and Management
    DOI
    10.3846/13923730.2013.802725
    Additional URLs
    http://www.tandfonline.com/doi/abs/10.3846/13923730.2013.802725#.VOGm9KOQ9QA
    ISSN
    1392-3730
    School
    Department of Civil Engineering
    URI
    http://hdl.handle.net/20.500.11937/34452
    Collection
    • Curtin Research Publications
    Abstract

    There is growing demand for cost effective and reliable floating production systems to maximize marginal and new deepwater fields worldwide. Floating Production Storage and Offloading (FPSO) vessels are considered to be the most economical and viable options to meet this demand. Yet, FPSO projects are prone to significant cost and schedule growth. On average, FPSOs have been reported to experience a 20% cost growth and are delayed by six months. Overruns and delays represent uncertainties for owners, contractors and financial institutions. In-depth interviews with twenty-three practitioners about their experiences with FPSO projects revealed that rework arising from design and construction errors were major contributors to cost and schedule growth. Key latent conditions contributing to rework are classified according to people, organization and project. Using retrospective sensemaking an examination of the determinant histories in a new build and conversion FPSO that experienced rework was undertaken. The sharing of experience(s) is deemed pivotal for reducing rework in future projects, particularly through the use of communities of practice that are able to stimulate situated learning to take place. A reduction in rework will not only reduce cost and schedule growth, improve operational performance and augment safety.

    Related items

    Showing items related by title, author, creator and subject.

    • Determining the probability distribution of rework costs in construction and engineering projects
      Love, Peter; Sing, Michael (2013)
      Rework arises due to design errors, changes and omissions during design and has been found to contribute to 52% of a project’s cost overrun. The statistical characteristics of rework costs experienced from contract award ...
    • Divergence or Congruence? A Path Model or Rework for Building and Civil Engineering Projects
      Love, Peter; Edwards, D.; Smith, J.; Walker, D. (2009)
      Rework has been identified as a major contributor to cost and schedule overrun in construction projects. Previous studies that have examined rework are based on a limited data sets and thus eschew generalizations being ...
    • The costs of rework: insights from construction and opportunities for learning
      Love, Peter; Smith, J.; Ackermann, Fran; Irani, Z.; Teo, Pauline (2018)
      © 2018, © 2018 Informa UK Limited, trading as Taylor & Francis Group. During the production of artefacts in construction, there is a likelihood for errors to be committed, which may need to be rectified so that they ...
    Advanced search

    Browse

    Communities & CollectionsIssue DateAuthorTitleSubjectDocument TypeThis CollectionIssue DateAuthorTitleSubjectDocument Type

    My Account

    Admin

    Statistics

    Most Popular ItemsStatistics by CountryMost Popular Authors

    Follow Curtin

    • 
    • 
    • 
    • 
    • 

    CRICOS Provider Code: 00301JABN: 99 143 842 569TEQSA: PRV12158

    Copyright | Disclaimer | Privacy statement | Accessibility

    Curtin would like to pay respect to the Aboriginal and Torres Strait Islander members of our community by acknowledging the traditional owners of the land on which the Perth campus is located, the Whadjuk people of the Nyungar Nation; and on our Kalgoorlie campus, the Wongutha people of the North-Eastern Goldfields.